What’s happening with this legislation and the new rules and regulations that will come from it is very much a moving target, and there’s a lot to cover when it comes to fracking, so this is the first of a four-part series. See part 2.
Note that the law’s constitutionality was challenged and that in July, the Commonwealth Court found some parts of the law unconstitutional; The part that limited local governments’ ability to write ordinances to restrict drilling in certain areas as well as the part that expanded waiver allowances to the siting standards involved in permitting an unconventional gas well.
The decision was appealed to the Supreme Court of PA, which heard testimony and arguments in October 2012, bu there’s been no indication of when a ruling will be forthcoming. In this first part, the focus will be on Act 13’s changes to permitting, notifications, bonding and reporting.
Reporting:
A well in the beginning stages (a so-called “spud”) requires new reporting. All operators must provide 24 hours’ notice of the date that drilling will commence to the department electronically via the department’s online oil and gas reporting application, which may be found at the DEP Oil and Gas Reporting – Electronic page. A full well record must now be filed with the DEP within 30 days of drilling. All information previously required is still required in the report.What Act 13 added in that’s new is identifying true vertical depths at which methane was encountered, other than in the target formation, and the country of origin and manufacturer of the tubular steel products used in well construction. When the well is completed, another report must be filed within 30 days of that completion (when the well is ready to produce).
- A descriptive list of the chemical additives used.
- The trade name, vendor, and intended use of each chemical additive
- A list of chemicals used
- The percent by mass of each chemical used
- The total volume
- List of water sources
- Pump rates, pressures, total volume used to stimulate a well
- Total volume of recycled water used
Permitting. The drilling permit application forms have been changed so that there are separate forms for conventional, unconventional and wells to be drilled in coal areas. There is an new form to describe ownership and control of companies seeking oil and gas well permits, as well as new bonding forms. All those may be found on the DEP’s Individual Forms page. The response rate of DEP to a permit application has been extended to as much as 75 days if the applicant is seeking a variance or waiver request on well siting restrictions. The DEP’s grounds for denying permits was expanded to include situations where the applicant, parent or subsidiary is in continuing violation of applicable state laws and regulations, or the applicant has failed to pay the required impact fee or file a report. Also note that a water management plan must be submitted and approved if any water will be withdrawn for drilling or fracking stimulation of an unconventional gas well. Approval must be sought through the appropriate River Basin Commission (Susquehanna, Delaware River or Great Lakes). This is a condition for any permit to be issued by the DEP.
Bonding.
- For up to 50 wells – $4,000/well not to exceed $35,000
- For 51-150 wells – $35,000 plus $4,000/well not to exceed $60,000
- For 151-250 wells – $60,000 plus $4,000/well not to exceed $100,000
- For more than 250 wells – $100,000 plus $4,000/well not to exceed $250,000
For wells with total well bore lengths 6,000 feet or greater:
- For up to 25 wells – $10,000/well not to exceed $140,000
- For 26-50 wells – $140,000 plus $10,000/well not to exceed $290,000
- For 51-150 wells – $290,000 plus $10,000/well not to exceed $430,000
- For more than 150 wells – $430,000 plus $10,000/well not to exceed $600,000
Notifications.
- The municipality in which the tract of land upon which the well to be drilled is located.
- Each municipality within 3,000 feet of the proposed unconventional vertical well bore.
- The municipalities adjacent to the well.
- Surface landowners and water purveyors with water supplies within 3,000 feet of a proposed unconventional well bore.
- Gas storage operators within 3,000 feet of the proposed unconventional vertical well bore.
As you can see, Act 13 is far-reaching in its effects on unconventional gas wells in the state of Pennsylvania. Stay tuned for Part 2 of this series, which will look into the environmental protection and setback provisions of Act 13 that have changed.